Project Title: Replacement Silo Project
Completed: 2018
Capital Value: £800k
Responsibilities: Acting as the principal contractor 4 number 12 ton, 16m x 3.5m diameter were installed during 4 separate phases overcoming difficult working at height and adverse weather conditions. A total of 40 ton of steel had to be replaced. Complex removal of the existing silo’s due to s/s failure from chloride attack. All work carried with zero accidents
Project Engineering Manager Comments:
“I would just like to say a huge thank you to you and your teams for all the hard work and team work that resulted in the delivery of the Silos project safely, on time and on budget